POOL CONSTRUCTION TIMELINE, PHASE BY PHASE
What happens on site in each phase, how long it takes, who does what, and the handful of things we need from you.
Your build at a glance
Five phases in the order they happen, then a 30-day startup while the finish cures. Tap any row to open that phase.
Just signed with us? Congratulations, this page is your build. Every pool we build in Bluffton, Hilton Head Island, and the surrounding Lowcountry follows this same sequence. If you only want the short answer on how long the whole thing takes, read how long it actually takes to build a pool.
Phase 1
Permitting & Engineering
Paperwork and approvals. What happens before we can start construction.
This is usually the longest stretch of most pool projects. Your plans have to clear your HOA's architectural review and then your county or town's permitting office, and both run on their own schedules rather than ours. We recommend requesting your HOA's submittal packet ahead of time.
Step by step
| Step | Who |
|---|---|
1 Contract signed | You |
2 Deposit paid | You |
3 Documents created | West Bay |
4 Samples visit | Together |
5 HOA submission | You |
6 HOA approval | Your HOA |
7 Permit submission | West Bay |
8 Utilities marked | West Bay |
9 Pre-site meeting | West Bay |
Your part
Permitting & Engineering invoice, due at permit approval
Phase 2
Excavation & Concrete Shell
The loudest and messiest part. You'll see your pool visino come to life.
Phase 3
Plumbing, Equipment, Tile & Coping
Pipes, equipment, and your first finish materials.
Phase 4
Decking
Your decking goes down around the pool and we start to wrap the project up.
Phase 5
Interior Finish & Fill
Your finish goes on and the pool fills with water.
After the build
The 30-Day Startup
Your pool holds water, but it is not finished yet. Swim after day 10.
Quick answers
Pool build timeline questions
- What are the phases of pool construction?
- A West Bay pool is built in five phases: permitting and engineering (8 to 12 weeks), excavation and the concrete shell (about 2 weeks), plumbing, equipment, tile and coping (2 to 3 weeks), decking (about 2 weeks), and the interior finish and fill (2 to 4 days). A 30-day startup follows while the finish cures, ending with the final inspection and your walkthrough.
- What happens first when you build a pool?
- Paperwork, not digging. After the contract and deposit, we hold a samples visit to lock in your materials, then produce the engineered pool plan and site plan. You submit that package to your HOA, we file for the county or town permit once the HOA approves, and utilities are marked before the crew mobilizes. Nothing happens in your yard until the permit is in hand.
- What inspections happen during a pool build?
- Three from your jurisdiction: a steel and bond inspection before the shell is shot, a bond wire inspection before the deck goes in, and a final inspection of the completed pool including your permanent barrier, gate hardware, and door alarms. We schedule all of them and run our own plumbing pressure test on top.
- What is the longest part of building a pool?
- Permitting and engineering. HOA architectural review and the local permit run on their own schedules and usually take 8 to 12 weeks combined, longer than the entire construction that follows. Requesting your HOA's pool submittal packet the week you sign is the single biggest thing that shortens it.
- When can you swim in a new pool?
- You can swim 10 days after the pool is filled. Toys, floats, ladders, and vacuums stay out for the full 30-day startup while the plaster cures, and the heater and salt system come online once startup ends.
Keep Going
More for your build
Timing on this page is estimated and will vary with the scope of your project, weather, inspection backlogs, HOA schedules, and any changes requested during construction. Your project manager is your source of truth for your specific schedule.